As federal contractors begin to grapple with the first government shutdown in several years, many are wondering how the shutdown will impact bid protests. This client alert provides the lowdown for how the shutdown will impact new and existing bid protests.

Government Accountability Office (GAO)

GAO is closed due to the lapse in appropriations.  Based on a message GAO issued earlier today, their electronic protest docketing system (EPDS) closed at noon today and will be inaccessible while GAO is closed.  That means parties cannot make new filings or access prior filings in EPDS during the shutdown.

So, if you cannot make filings in EPDS, what happens to GAO protest deadlines during the shutdown?  GAO will extend the deadlines as follows:

Court of Federal Claims (COFC)

Unlike GAO, our understanding is that the COFC will remain open and all deadlines will remain in effect.  As a result, COFC may be the better option during the shutdown for those procurements that permit a protest in either forum.  Additionally, the United States Court of Appeals for the Federal Circuit confirmed that it will remain open for business during the shutdown and all filing deadlines and oral arguments will proceed as scheduled.

FAA’s Office of Dispute Resolution for Acquisition (ODRA)

ODRA released guidance indicating it is taking a unique approach to handling deadlines during the shutdown. Per ODRA’s guidance, deadlines for the government will be tolled during the shutdown but deadlines for private parties will not be affected and will only be extended for good cause shown.  As a result, contractors should assume that new protests, comments, supplemental protests, and similar filings are still due as originally scheduled.

Agency Level

The shutdown’s impact on agency-level protests will vary from agency to agency.  For agencies that are still open for business, protest deadlines should remain in effect.  For agencies that are shut down, contractors should expect delays in decisions on pre-existing protests but, in the absence of definitive guidance from the agency, should adhere to a filing deadline based on an award or debriefing received prior to the shutdown.

If you have questions about how the shutdown may impact your existing protest, or if you need help in deciding how to handle a potential new protest or the impact on a CICA stay during the shutdown, please contact Jon Williams, Katie Burrows, or Eric Valle from PilieroMazza’s Bid Protests Group.